The new section of median barrier between 295 North and South just below Bell road has ben completed. The new sign structure is still awaiting installation.
Here is the temporary path the exit will take from 76 East to 294 North.
This picture shows it connecting to the new exit bridge.
The trees between 76 East and Willow place have been cleared.
Here is a look at that same area from the Browning Road overpass.
The land has been cleared off of Essex Ave for one of the new sections of the Bellmawr Park Mutual Housing and a construction trailer is in place.