Thursday, November 24, 2022

Missing Moves November 2022


The main structure of the new Missing Moves ramps are pretty much complete with two exceptions, a gap where the ramp passes over 42, and a second gap where it passes over 295. The center support for the 42 gap is currently being built. A steel cross support for the ramp over 295 was recently installed along with the first couple of support beam for the road bed.

Here is an aerial photo thanks to 42Freeway.com, along with some of my photos from the ground. 







Additional support beams are staged near by.
 


On the north bound side of 295 work continues on fencing near the Creek Road overpass and barriers along the new ramp to 42 South. 




Sunday, November 6, 2022

Browning Road Overpass November 2022

Equipment is in place to start working on the second bridge abutment for the new Browning Road overpass. I am assuming the pile driver will be used to but in sheet pile to retain the earth so that the old abutment can be removed. 




 

Wednesday, November 2, 2022

Missing Moves November 2022

The concrete has been poured for the first part of the center support from the ramp from 42 North to 295 South. Sitting next to the support is the form for the top portion of the support.