Wednesday, November 21, 2018

November 2018

Work continues on the tunnel that will carry  the traffic coming from 76 East under the new 295 main line

DSC03428


DSC03429


The beams for the roof of the tunnel were set a couple weeks ago then covered in corrugated steel and recently that have started pour the concrete roof. In the upper right you can also see some new noise barrier work.

DSC03408


DSC03435


DSC03402


DSC03406


Paving has been done in the area after the tunnel.

DSC03431


The support columns for the new 295 mainline.

DSC03375


Work in the area between the Al-Jo curve and the Browning Road overpass is almost complete for now. The area has been paved and a fence installed on top of the retaining wall.

DSC03382


There is still a lot of work going on below the Browning Road overpass

DSC03385


The have started to excavate some pits in this area which I assume are going to be for support columns for the main line overpass.

DSC03397