Over the past few weeks work has been focused on the ramp from 42 North to 295 North and the 295 North part of the new mainline overpass. The concrete road bed has been poured on the 42 North Ramp and the decking and rebar has been placed for the 295 North side of the mainline which should be ready for concrete soon.
Over the past couple days they have started to install the steel beams for the 295 South section of the mainline overpass which is the last steel that needs to be installed to finish the overpass.