I-295/I-76/Route 42 Direct Connect
Sunday, April 21, 2024
Direct Connect April 2024
Sunday, February 18, 2024
Direct Connect February 2024
Small update. Looks like they are starting to rebuild the columns that are at the end of the mainline road. These will support the end of the overpass over Browning Rd and 76.
Sunday, January 21, 2024
Direct Connect January 2024
For the first time in a while, work has started on another section of the project. A concrete form has been installed on the top of the support columns nearest Browning Road. These will eventually carry the new mainline over 42 and Browning Road.
Sunday, December 31, 2023
Direct Connect December 2023
Here is a look at the retaining wall that was built between the tunnel to 295 North and the 295 South lanes.
Wednesday, November 29, 2023
Missing Moves is Open!
On Tuesday morning the missing moves ramp opened for public use! There is still some line painting going on over night and some cleanup tasks but the project is mostly complete. Unlike the Direct Connect Project this project went very smoothly and actually completed earlier then originally planned, despite the fact that it started in the early days of COVID.
The ramp from 55 North to 42 North has been expanded to 2 lanes and when I drove this around 6:30 AM Tuesday morning there was not delay at the end of 55, I continued full speed all the way from 55 to 295 South.
Here are some pictures going from 42 North to 295 South later on Tuesday.
You can just see the stop of the Philadelphia skyline in the distance.
Thursday, November 23, 2023
Direct Connect November 2023
For the last few months the focus of the work on the Direct Connect project has been the reconstruction of the collapsed section of roadway.
Over the past few weeks they have been driving in pilings in the area of where the center of the road and these pilings have been capped off in concrete. This appears to be a temporary retaining wall that is allowing them to excavate out the front portion of the road which is where the problem that lead to the collapse occured.
Friday, November 17, 2023
Missing Moves November 2023 - Part 2
On 295 North paving have been completed and the road re-striped into the final lane configuration.
The area under the ramp near Harding Ave has been cleaned up and hydro-seeded.