Sunday, October 22, 2023

Missing Moves Mid October 2023

 Here is a look at the Missing Moves work along 295 North. 


Landscaping and guardrails have been installed.




Guard rails leading up the Big Timber Creek Bridge


Just like on the south bound side, work is being done under the bridge. This is a special truck designed to provide access under the bridge from on top. 

Small section of guardrail still needing completion. 


A crash attenuator has been installed at the start of the ramp to 42 South.

Stripping have been applied to the ramp.






Tuesday, October 17, 2023

Missing Moves Mid October 2023

 Barriers have been removed along 295 South from the new ramp all the way down to Delsea Dr. 




Guard rails and fencing have been installed.




More new guardrails and new landscaping.



New landscaping along the north bound side.


Over on the 42 side, the building on Harding Ave that was under the ramp has been demolished and the site cleaned up.




Friday, October 6, 2023

Missing Moves October 2023

Work is rapidly finishing up on the missing moved project and it should be open by the end of the year, but I guessing sooner.

Signs are up for the new ramps.

Paving has been done along 295 North between Delsea Drive and the Big Timber Creek Overpass.


Concrete work is complete on the 295 North Bound side of the bridge over Big Timber Creek. 



Paving along 294 North between the Big Timber Creek bridge and the ramp to 42 South.

Paving of the shoulder along the ramp to 42 South. You can also see the light posts are all powered up now.


Barriers have been removed along the ramp from 42 North to 295 South.



Barrier now starts at the end of the ramp.


Paving from the ramp from 42 North to the Big Timber Creek bridge.

Big Timber Creek bridge on 295 South is looking complete. The piece of equipment on the bridge is used to work over the side of the bridge. 

Paving and between the Big Timber Creek bridge and Delsea drive. They are also finishing up the cleanup of the area next to the road. 



Over on 42 the barriers have been removed exposing the new center median barrier. 


Sunday, August 27, 2023

Missing Moves August 2023, 295 South

 Here is a look a the South bound side of 295.


The end of the ramp from 42 North to 295 South has been completed.



Curbing, drainage and paving work from the end of the ramp down to the Big Timber Creek bridge.




Concrete has been poured for the the south bound side of the bridge over Big Timber Creek.


A few days later they have started to pour the concrete barrier along the edge of the bridge.


Widening of the road from the Big Timber Creek bridge down to the Delsea Drive exit. 



Wednesday, August 23, 2023

Missing Moves August 2023, 295 North

The missing moves project is finally in it's home stretch and is expected to be complete this fall. Let's look at the progress along 295 North.

These pictures show the day that the concrete was poured for the deck of the bridge over Big Timber Creek.



After the concrete was poured and covered in plastic to protect it as it cures.

Just beyond the bridge is this pile of earth where the deceleration ramp will eventually be. This has been here since very early in the project so I assume it is being used to compact the earth in this area before the road is built on it. 


Paving work has been done on the approach to the ramp from 295 North to 42 South. 

Concrete pad is in place for the crash attenuator that will be at the start of the ramp. 

Paving has also been done along the side of the ramp to form a shoulder along 295 North. 


Sunday, August 6, 2023

Missing Moves August 2023

Work continues on the bridge over Big Timber Creek. These pictures show the work on the north bound side of 295. The equipment used to smooth the concrete has been brought in so pouring the concrete bridge deck is not far off. 


Work on the bridge deck.


Rebar being installed for the bridge deck. 



Work has started on the area between Big Timber Creek and the start of the ramp to 42 South. This will become the deceleration lane for the ramp. 





On the south bound side work has started to complete the barrier starting from the ramp from 42 North.