Missing Moves August 2023, 295 South

 Here is a look a the South bound side of 295.


The end of the ramp from 42 North to 295 South has been completed.



Curbing, drainage and paving work from the end of the ramp down to the Big Timber Creek bridge.




Concrete has been poured for the the south bound side of the bridge over Big Timber Creek.


A few days later they have started to pour the concrete barrier along the edge of the bridge.


Widening of the road from the Big Timber Creek bridge down to the Delsea Drive exit. 