The missing moves project is finally in it's home stretch and is expected to be complete this fall. Let's look at the progress along 295 North.
These pictures show the day that the concrete was poured for the deck of the bridge over Big Timber Creek.
After the concrete was poured and covered in plastic to protect it as it cures.
Just beyond the bridge is this pile of earth where the deceleration ramp will eventually be. This has been here since very early in the project so I assume it is being used to compact the earth in this area before the road is built on it.
Paving work has been done on the approach to the ramp from 295 North to 42 South.
Concrete pad is in place for the crash attenuator that will be at the start of the ramp.
Paving has also been done along the side of the ramp to form a shoulder along 295 North.