Work on the project is starting to pick back up, mainly around the foundations for what will become the overpass supports. Here are some pictures of the area along 42 North just after the Browning Road overpass. First is the section of the plans for this area, I have circles the location of three foundations that are being build.
In this picture you can see the yellow forms for the foundation that was poured a while back. This is the foundation circled in blue on the plans.
A pit has been dug between the existing foundation and the highway, this will be for the foundation circled in red on the plans.
Another pit has been dug below where the temporary Browning Road overpass will go. This is for the foundation circled in yellow.
Here is a look at the area from 42.
Works is also going on at two other locations were there will eventually need to be bridge supports. There are ground heaters setup at these locations probably to facilitate concrete work.
Did you know that the 42/295 Missing Moves project already began?
ReplyDeleteYes, I just did a post today showing the start of the work.
DeleteDid you also get some updates for the Direct Connection project?
DeleteI looked but didn't see any change in the past two weeks.