Saturday, June 23, 2018

June 2018


Demolition of the Bellmawr Mutual Housing units is now in full swing. I believe a total of 5 buildings will be removed.


Here you can see the first one has been removed right where they are starting to extend the ramp.

DSC03114


Siding stripped from the second building.

DSC03116


Excavator in place to start the demolition of the second building.

DSC03119


… and a day later the second building was gone.

DSC03125


Looking over the area where the first building was.

DSC03126


Third building is having it’s siding stripped.

DSC03127


Work has started on the retaining wall along 295 South between the Al-Jo curve and Browning road.

DSC03122