Some new sheet pile being put in below the cemetery leading up the to retaining wall that was build over the past year.

DSC02809


Demolition of the old 76 East to 295 North overpass has started. They are doing periodic overnight lane closures to do this.

DSC02812


Work continues on the area along 295 South just before Browning Road.

DSC02813


Work also continues on the area where the supports for the temporary Browning road bridge will be.

DSC02814


A temporary retaining wall has been installed along 295 South just below the Browning Road overpass and they have started to excavate between the wall and the road.