Saturday, April 2, 2016

March 2016

Work continues on the new ramp for 76 east to 295 north.

DSC01523

 

Here you can see the top of the new retaining wall being build along 76 east. The steel beams sticking up will be the start of the new overpass. You can see the concrete support for the other end in the background.

DSC01526

 

Work along the edge of the cemetery continues. In this picture you can see some green rebar sticking up out of the pit which I assume is for retaining walls.

DSC01529

 

In this picture you can see them pumping concrete in that area.

DSC01537

 

The retention pond within the 295 to 168 ramp has been cleaned up and a fence has been put around it.

DSC01532

 

Work continues at the new ramp along the right side of 295 S before the Al-Jo curve. The fence along the edge has been removed and they have started to fill in between the ramp and the edge of the road.

DSC01535

 

The end of the ramp at the start of the Al-Jo curve.

DSC01538

No comments:

Post a Comment