Photo Update 9/2014

Work is progressing nicely on the Bell Road overpass. Concrete aprons have been poured on both sides.

IMG_4909

 

They started pouring the concrete for the road bed today.

IMG_4933

 

Along 295 S they have started to put concrete cap blocks on the retaining wall.

IMG_4918

 

New traffic lights on either side of the Creek Road overpass are working now but are just blinking yellow for now.

IMG_4925

Work at the Essex Ave overpass.

IMG_4926

 

The support on one side of the Essex Ave overpass has been demolished.

IMG_4927