With work complete on the second new bridge abutment for the Browning Road Overpass a lane shift has been done to allow work to continue. The far right lane which connects 42 North to 295 North has been shifted over to the right. This shift is needed to create a work area between the North and South bounds lanes of 42 so that the old bridge supports can be demolished and new ones built. There will also be some supports for the new 295 main line overpass. In the drawing below you can see the location of the new pier names "Pier 2".
Tuesday, September 10, 2024
Friday, August 2, 2024
Browning Road Overpass July 2024
The new Jersey barrier has also been extended part of the way under the temporary overpass.
Sunday, June 23, 2024
Browning Road Overpass June 2024
There hasn't been much visible work on Direct Connect recently. The one area that is seeing clear progress in the Browning Road Overpass.
Here is a picture from a couple weeks ago showing the concrete forms on the new bridge abutment.
Wednesday, May 15, 2024
Browning Road Overpass May 2024
The retaining wall for the second Browning Road bridge abutment has been constructed in front of the previously constructed support columns.
Sunday, April 21, 2024
Direct Connect April 2024
Sunday, February 18, 2024
Direct Connect February 2024
Small update. Looks like they are starting to rebuild the columns that are at the end of the mainline road. These will support the end of the overpass over Browning Rd and 76.
Sunday, January 21, 2024
Direct Connect January 2024
For the first time in a while, work has started on another section of the project. A concrete form has been installed on the top of the support columns nearest Browning Road. These will eventually carry the new mainline over 42 and Browning Road.