Browning Road Overpass September 2024

With work complete on the second new bridge abutment for the Browning Road Overpass a lane shift has been done to allow work to continue. The far right lane which connects 42 North to 295 North has been shifted over to the right. This shift is needed to create a work area between the North and South bounds lanes of 42 so that the old bridge supports can be demolished and new ones built. There will also be some supports for the new 295 main line overpass. In the drawing below you can see the location of the new pier names "Pier 2". 




 