Sunday, November 6, 2022
Browning Road Overpass November 2022
Wednesday, November 2, 2022
Missing Moves November 2022
The concrete has been poured for the first part of the center support from the ramp from 42 North to 295 South. Sitting next to the support is the form for the top portion of the support.
Sunday, October 30, 2022
Direct Connect October 2022
Preparation work has started on the area around the collapsed wall to get ready for reconstruction which should start soon.
Wednesday, October 26, 2022
Creek Road Overpass
On the Creek Road overpass over 295, traffic has been shifted onto the newly constructed south side of the bridge. The north side once again been blocked off so the final work can be complete there which will include adding the pedestrian walkway.
Sunday, October 16, 2022
Missing Moves October 2022
With the Creek Road overpass mostly complete there is now room to complete the ramp that will come from 42 North to 295 South
Saturday, October 8, 2022
Missing Moves October 2022
Work has begun on the support in the center median of 42. This is the final support needed to connect the two parks of the missing moves ramp that is already under construction.