Sunday, October 30, 2022

Direct Connect October 2022

Preparation work has started on the area around the collapsed wall to get ready for reconstruction which should start soon.





 The shoulder along the ramp from 42 North to 295 North has been widened and some drainage improvements have been made. 




Final work on the first of the new Browning Over overpass abutments. 



Preparation work in between the lanes of 76 East for a new support for the Browning Road overpass. The old overpass had once center support, but the new longer overpass  will require two. 