Work continues on the new mainline overpass and the new ramp from 42 north to 295 north. Most of the steel is in which just one last section of the south bound lanes incomplete.
Metal sheeting for the bridge deck of the main line overpass has been staged at the southern end of the project.
At the southern end of the mainline they have started to pour the concrete Jersey barrier that will seperate the north and southbound lanes of 295.