Sunday, May 11, 2025

Direct Connet May 2025

Here is a look at the  support columns being built betwen the north and south bound lanes of 42. Some of these will be for the new 295 mainline overpass, others will be for the ramp from 42 north to 295 north. You can see the start of that ramp on the right which was built quite some time ago. 






With the ramp to 295 south now re-routed is has freed up space for other work in this area. Here the foundation for another support column is being contstructed. 




Here is a look at the old ramp to 295 south. The barriers have been removed and they have started to clean up the side of the slope. The retining wall for the new 295 mainline will eventually continue into this area. 