Saturday, February 18, 2023

Direct Connect February 2023

Work has begun to demolish the Browning Road bridge abutment on the 76 W side of the road. You can see here the earth being cleared out behind it.


Some prep work has been done at the site of the collapsed section of retaining wall, but no actual re-construction work has started yet. 



Work continues to between the lanes of 76E/42S. This appears to be ground preparation for the bridge supports that will be built in this area. 






 

No comments:

Post a Comment