Sunday, April 12, 2020

April 2020


I looks like some work has been going on the past week. The retaining wall by the cemetery has started to wrap around the support columns. The will eventually form the end of the of the new 295 mainline where it transitions into an overpass over 42.

IMG_20200411_094633


More land clearing has been done for the missing moves project. Here you can see some clearing along 295 North, just above Almonesson Rd.

IMG_20200411_094452


IMG_20200411_094456


Some more land clearing along 295 North between Almonesson Rd. and Creek Rd.

IMG_20200411_094522


Here is another look at some of the clearing along 295 South just above Creek Rd. It’s hard to see in this picture but the a staging area has been setup in this area.

IMG_20200411_122625