Contact 2 seems to be wrapping up, so a lot of cleanup work is going on. Here is a look at the area between 76 West and the 295 North ramp. The area has been cleaned up and graded. The line of “bumps” poking out of the earth is going to be where the ramp from 295 South to 42 South will eventually be. This will be built as part of the fourth contract.
They have started to close in the hole in the retaining wall for the new main line. This was used for construction access to that area.
Here is a look at the northern portion of the main line ramp. Guard rails and sign structures have been installed.
A lot of cleanup work has been done in the area between the new main line and the ramp from 295 South to 76 West.
Here is another look at the area where the ramp from 295 South to 42 South will eventually be built.
The start of the ramp from 42 North to 295 North has been paved.
Where are the updates for this month?
ReplyDeleteIt seems that Contract #3 is at a stand still. Any ideas of why the work has stopped?
ReplyDeleteBecause the work that still needs to be completed is dependent on the Browning Road overpass being completed.