The temporary ramp along 295 South before the Al-Jo curve is almost complete. Most of the barriers are in, it’s paved and the lights have been installed. Signs along 295 say that there will be a traffic pattern change on or about July 8th, so it appears that is when the ramp will open. Of course the governor’s executive order shutting down road work might effect this, I am not sure if this order impacts this project.
Work continues on the ramp from 76 East to 295 North.
A very large crane is now on site in this area which will probably used to install the steel beams for the ramp.
Parts of the retaining wall being build next to the cemetery are now visible over the edge of the pit.
The ramp next to the Bellmawr ball fields has been fenced off until further work happens later in the project.
Work on the new Creek Road overpass is almost complete.
The intersections at Creek road are almost complete.
Still some work going on on this corner.
No comments:
Post a Comment