Work continues on the temporary bridge next to 295 Southbound before the Al-Jo curve. This image shows where the bridge is being built. This will allow traffic to be moved temporarily onto the new ramp to make room for construction of the new ramp from 295 South to 42 South.
Here are two of the pre-cast beams being used to build the bridge.
The first few beams in place.
A later stage of construction with all the beams in place and temporary safety railings in place.
Close up look at the bridge.
The new ramp between the 295 South ramp and the Bellmawr ball fields. The noise barrier is complete and they have started to clean up the slope on the other side which is temporary until the other side of the ramp is eventually built.
Trees have been planted just beyond the work area on 295 South. This is one of many signs that Contract 1 of the project is starting to wrap up. Contact 2 is ongoing and Contract 3 will start this Fall.
No comments:
Post a Comment