Now that 295 North traffic has been moved on the new ramp at 42, work has begun to move the other two ramps (ramp to the 76 express land and ramp to 295 South) onto the center of the Essex Ave bridge so that the final section of the bridge can be rebuilt. Here you can see work going on to move he express ramp.

DSC01275 

DSC01261

DSC01277

Here is the work going on to move the ramp to 295 South over to the of the Essex Ave bridge.

DSC01286

DSC01287

In other parts of the project, traffic is now running on the new section of the Creek Road bridge over 42 so work can begin to re-build the other half.

DSC01279

 

Location of a future pumping station along Browning road.

DSC01280

Construction continues on the next section of the new ramp at the start of the Al-Jo curve.

DSC01282