A major milestone was reached this week when the first steel was set for the new 295 main line overpass. There beams connect the newly reconstructed section to the first pier by the Browning Road overpass.
I-295/I-76/Route 42 Direct Connect
Saturday, September 20, 2025
Thursday, September 11, 2025
Direct Connect September 2025
Thursday, August 21, 2025
Browning Road Overpass August 2025
The temporary Browning Road overpass has been fully pulled back into the staging area by the cemetary where it is being disassembled. They have also removed the termporary supports that were used to remove the bridge and have started to demolish the temporary concrete columns in the middle.
Wednesday, August 13, 2025
Browning Road Overpass August 2025
The second move of the temporary Browning Road overpass has been completed, now just leaving the extended portion hanging over the road. They have also begun to disassemble the temporary supports that were put in place to help with the bridge removal.
Wednesday, August 6, 2025
Browning Road Overpass August 2025
Saturday, July 26, 2025
Browning Road Overpass July 2025
Prep work continues for the removal of the temporary Browning Road overpass. The bridge deckings has been mostly removed. There is one section left that I assume is staying for some reason. The bridge if no longer connected to the middle support columns and is now on rollers on the temporary columns.
Saturday, July 12, 2025
Direct Connect July 2025
With the new Browning Road overpass complete and the rebuild of the collapsed section nearing completion attention has turned to building the support columns that will eventually hold up the new 295 overpass. Here is a picture of that area thanks to 42 Freeway.