Sunday, May 29, 2022

Direct Connect May 2022

 The work on the direct connect project continues to be focused on the Browning Road overpass reconstruction. Work has started to build the new bridge abutment on the 76 East side of the road. Here you can see that they have started to create the concrete support columns. 






Sunday, May 22, 2022

May 2022

There has been a lot of work going on with both projects recently but it has been hard to get good photos of. Instead I would recommend checking out a great video update over at 42 Freeway. This has some good drone footage of the work on both projects. 




Sunday, April 17, 2022

Missing Moves April 2022

The left side of the ramp from 55 North to 42 North has been closed off to allow for construction at the end. When this project is complete the 55 ramp will have two lanes. 



A look at the ramp from 42 North to 295 South. 




A closer look at the ramp where it will eventually cross over 42 North.



The new exit that will replace the current one to Leaf Ave. This one connects to Benigno Ave. 


Here is a look at the exit from Benigno Ave.


Work along 42 North just before the new ramp to 295 South.


The new section of road that will directly connect Benigno Ave to Edgewood Ave.




Saturday, April 9, 2022

Browning Road Overpass 4/5/2022

The remainder of the Browning Road overpass bridge deck has been removed leaving just the center supports and the second abutment. 



 

Sunday, March 27, 2022

Browning Road Overpass 3/26/2022

The first of the Browning Road overpass bridge abutments has been removed so work can now start on the new one. 



 

Here you can see what remains of the Browning Road overpass bridge structure which should be removed soon.

Saturday, March 26, 2022

Missing Moves 3/26/2022

A new traffic pattern has been put in place on 295 South just below Creek Road. The left lane now splits off and goes over the newly constructed section of the bridge over Big Timber Creek. This has opened up a space for work between the left and right lanes.





Pilings in place for the new retaining wall at the Creek Road overpass.




 

Sunday, March 20, 2022

Missing Moves Ramp

These pictures are from a few weeks ago and show the steel being installed for the ramp from 295 North to 42 South over Coolidge Ave in Bellmawr.