Thursday, December 23, 2021

Missing Moves 12/2021

 More steel has been added to the ramp from 42 North to 295 South.





Saturday, December 11, 2021

Missing Moved 12/2021

At the Big Timber Creek bridge they have started to pour the concrete or the abutments on both sides of the bridge and started to install more of the concrete beams. 





Here is one of the beams waiting to be installed.




This is the section of the missing moves ramps between Creek Road and Leaf Ave. This section will be ground based so they have started to build up the earth to the height of the finished road. 






Friday, December 3, 2021

Missing Moves 12/2021



More steel has started to go in for the Missing Moves project. This will be the ramp from 42 North to 295 South right before it passes over 42.



In this picture you can see the temporary supports for the next section of the ramp.

 

Beams staged along 42 North.




Tuesday, November 16, 2021

Missing Moves November 2021

 The old Creek Road support on the South bound side of 295 and work has started to build the new one.



Capping is being added to the top of the retaining wall the forms the ramp from 42 North to 295 South.




Here is a look at the ramp from the Creek Road overpass.


Wednesday, November 3, 2021

Missing Moves November 2021

 

The first pieces of steel have been installed in the Missing Moves project. These are for the ramp from 295 north to 42 south as it passes over Creek Road.



Friday, October 29, 2021

Missing Moves October 2021

 With the new section of the Creek Road overpass complete demolition of the other half has started. 






Tuesday, October 19, 2021

Browning Road Overpass

 The temporary Browning Road overpass has finally opened making way for he demolition and reconstruction of the existing bridge.

Here are some pictures from before the opening of the temporary bridge.



Here are some pictures driving over the new bridge. It is one lane in each direction, with a sperate pedestrian walkway down the side opposite the old overpass.