Wednesday, September 30, 2020

September 2020–Direct Connect


Some interesting work on the Direct Connect project this week. They have started to build more of the overpass supports by the cemetery.


PXL_20200928_210808251


PXL_20200928_222909157


Here is a view of the work from Browning Road.

PXL_20200928_223428466

Tuesday, September 15, 2020

September 2020–Missing Moves


Quick update today. Part of the Creek Road bridge structure has been removed and the end of middle support cut off. This is to make room for the new bridge which will be built next to the current one.

IMG_20200914_185145

Monday, September 7, 2020

Missing Moves–Lead Ave Exit

As part of the Missing Moves project the exit connecting 42 to Leaf Ave will be re-configured. Here is a rough sketch of what it will look like. The exit will move a short distance south along Benigno Ave. Benigno will also be shifted to line up with Edgewood Ave. The current exit will be removed along with a small section of Benigno.

LeafAveExit


Here is a picture from the RTV Systems simulation of the project showing the new configuration.

image


In this picture from a few month ago you can see the layout of the new exit.

8e6b4eb0-b792-49f0-abf8-d87fc3f5001b


In this picture you can see the re-alignment of Benigno Ave.

IMG_20200906_143226

September 2020–Missing Moves


Here is a look at the current work going on at the bridge over Big Timber Creek

IMG_20200906_085125

IMG_20200906_085126

IMG_20200906_085127


The support for the ramp going to 295 South. I believe they will be building retaining walls on either side of this structure to form the end of the ramp.

IMG_20200906_144447


A bed of gravel has been put down where the end of the ramp will be.

IMG_20200906_144451


Here is the same area looking down from Creek Road.

IMG_20200906_143535


Demolition has started on the Creek Road overpass. Part of it will need to be removed before they can start building the new overpass which will be slightly further north then the current one.

IMG_20200906_144452


IMG_20200906_144454


A look at the overpass supports being built near Coolidge Ave.

IMG_20200906_142914


IMG_20200906_142919


IMG_20200906_142924


Construction between 42 and Benigno Ave. There will eventually be more supports of the ramps here.

IMG_20200906_143215


IMG_20200906_143219

Sunday, August 23, 2020

Missing Moves August 2020


Here is a look at the work going on at the Big Timber Creek bridge.

00000IMG_00000_BURST20200823112316202_COVER


00100lrPORTRAIT_00100_BURST20200823112322072_COVER


IMG_20200823_085950


IMG_20200823_085951


The support for the ramp along 295 South

00000IMG_00000_BURST20200823112252864_COVER


IMG_20200823_090017


Work along 295 North.  This will be to accommodate the widened highway.

IMG_20200823_090012

Wednesday, August 12, 2020

August 2020–Missing Moves


Here is the current progress on the bridge of Big Timber Creek. You can see that they have started to demolish part of the bridge deck and supports. The project requires the widening of the bridge and the plans mention bridge deck rehabilitation, so I am not sure if till be entirely replaced or not.

IMG_20200808_090324


IMG_20200808_090326


This structure is being built along 295 South just above Creek Road. This is where the overpass will end and transition into a ramp down to 295 South.

IMG_20200808_090350


A barrier has been installed on the Creek Road overpass over 295. That side of the overpass will be demolished to make room for the new overpass.

IMG_20200808_141146

Thursday, August 6, 2020

Update Construction Schedule


NJDOT has recently updated the construction schedule. Completion is not target for 2027, 6 years later then originally planned. One half of the ramp is planned to open about a year before the other.


image