Friday, August 2, 2024

Browning Road Overpass July 2024

Work on the second abutment for the new Browning Road Overpass appears almost complete. The concrete supports on the top of the abutment have been poured and the retaining wall next to it has been capped off. The Jersey barrier along the bottom of the wall has also been poured. 

 

The new Jersey barrier has also been extended part of the way under the temporary overpass.



Sunday, June 23, 2024

Browning Road Overpass June 2024

 There hasn't been much visible work on Direct Connect recently. The one area that is seeing clear progress in the Browning Road Overpass. 

Here is a picture from a couple weeks ago showing the concrete forms on the new bridge abutment. 



Here are two more recent pictures.



Once the second abutment is complete, they next step will be to demolish and rebuild the second set of support columns. The new support is a little closer to the North Bound lanes of 42 then the current supports, and there is also a support for the new 295 mainline overpass in this area. This may require lane shift to make room. 


Wednesday, May 15, 2024

Browning Road Overpass May 2024

The retaining wall for the second Browning Road bridge abutment has been constructed in front of the previously constructed support columns.  



Sunday, April 21, 2024

Direct Connect April 2024


There hasn't been a lot of easily visible work on the Direct Connect project over the past few months but recently there were a few visible changes. 

Work has started up again on the second bridge abutment for the Browning Road overpass. The first was complete a while back, and the other side was demolished but then work appeared to stop. In the picture below you can see the four rebar cages that will for support columns for the new abutment. 



Another recent change, move concrete structures have been poured on top of the columns which will support the new 295 main line overpass. 
 


The rest of the work has focused on rebuilding the collapsed section of the roadway. A temporary retaining wall has been build to hold up the back portion of the roadway so work can be done to create a stronger foundation for the from retaining wall. 





Sunday, February 18, 2024

Direct Connect February 2024

Small update. Looks like they are starting to rebuild the columns that are at the end of the mainline road. These will support the end of the overpass over Browning Rd and 76. 




Sunday, January 21, 2024

Direct Connect January 2024


Work continues to rebuild the collapsed section of the new mainline road. Pilings are still being driven in to the front section of the road.





 

For the first time in a while, work has started on another section of the project. A concrete form has been installed on the top of the support columns nearest Browning Road. These will eventually carry the new mainline over 42 and Browning Road. 




Sunday, December 31, 2023

Direct Connect December 2023

Here is a look at the retaining wall that was built between the tunnel to 295 North and the 295 South lanes.  




Work continues to re-build the collapsed section of the new main line roadway. A temporary retaining wall has been build to hold up the back section of the roadway. They have now started to driving pilings that will form the foundation for the front section of the roadway. 





Work hasn't started on the second Browning Road overpass abutment yet, but it appears that some work was being do to stabilize the temporary retaining walls.