There has a been a lot of work going on all around the Browning Road Bridge Area.
A few weeks ago a new traffic pattern was put in place that shifted the traffic coming off the Al-Jo curve and going to 42 South further to the left so it now merges close to the Browning Road overpass. This actually brings this merge back to the way it was a long time ago.
This lane shift has opened up room to build the four remaining support columns which they have started to dig foundations for.
While all this work is going on, more pieces of steel are being staged. These are sitting on the shoulder along 295 South just above the Al-Jo curve. These appear to be the pieces that will span between the column over the highway and will support the beams that actually carry the road.