A major milestone was reached this week when the first steel was set for the new 295 main line overpass. There beams connect the newly reconstructed section to the first pier by the Browning Road overpass.
Saturday, September 20, 2025
Thursday, September 11, 2025
Direct Connect September 2025
The temporary Browning Road bridge has been complete dissasembled and removed. The crane in that area was used to assemble a support column in the location where the bridge was.
The foundation for this column had been built before the temporary Browning Road bridge was installed, so once removed this column went in very quickly. This will eventually carry the new 295 main line overpass over Browning Road.