The temporary Browning Road overpass has been fully pulled back into the staging area by the cemetary where it is being disassembled. They have also removed the termporary supports that were used to remove the bridge and have started to demolish the temporary concrete columns in the middle.
Thursday, August 21, 2025
Wednesday, August 13, 2025
Browning Road Overpass August 2025
The second move of the temporary Browning Road overpass has been completed, now just leaving the extended portion hanging over the road. They have also begun to disassemble the temporary supports that were put in place to help with the bridge removal.
Wednesday, August 6, 2025
Browning Road Overpass August 2025
The first phase of the removal of the temporary Browning Road overpass has been completed. Overnight the bridge was pulled back onto an open piece of land by the cemetary leaving it sitting on just one of the two temporary supports. Over the next few weeks that section will be dismantled and then a second pull will happen to remove the rest of it.
42Freeway has a great drone video of the process on Facebook.