A major milestone was reached this week when the first steel was set for the new 295 main line overpass. There beams connect the newly reconstructed section to the first pier by the Browning Road overpass.
Saturday, September 20, 2025
Thursday, September 11, 2025
Direct Connect September 2025
Thursday, August 21, 2025
Browning Road Overpass August 2025
The temporary Browning Road overpass has been fully pulled back into the staging area by the cemetary where it is being disassembled. They have also removed the termporary supports that were used to remove the bridge and have started to demolish the temporary concrete columns in the middle.
Wednesday, August 13, 2025
Browning Road Overpass August 2025
The second move of the temporary Browning Road overpass has been completed, now just leaving the extended portion hanging over the road. They have also begun to disassemble the temporary supports that were put in place to help with the bridge removal.
Wednesday, August 6, 2025
Browning Road Overpass August 2025
Saturday, July 26, 2025
Browning Road Overpass July 2025
Prep work continues for the removal of the temporary Browning Road overpass. The bridge deckings has been mostly removed. There is one section left that I assume is staying for some reason. The bridge if no longer connected to the middle support columns and is now on rollers on the temporary columns.
Saturday, July 12, 2025
Direct Connect July 2025
With the new Browning Road overpass complete and the rebuild of the collapsed section nearing completion attention has turned to building the support columns that will eventually hold up the new 295 overpass. Here is a picture of that area thanks to 42 Freeway.
Friday, July 11, 2025
Browning Road Overpass July 2025
A few weeks ago the new Browning Road overpass opened, so work has now turned to removing the temporary overpass. Most of the bridge decking has been removed and the temporary support columns have been setup. I assume this will be removed just like it was installed, sliding it over to the cemetery side and disassembling it piece by piece.
Tuesday, June 24, 2025
Browning Road Overpass Now Open!
Thursday, June 12, 2025
Browning Road Overpass June 2025
The new Browning Road overpass is nearing completion and word is that it will open on June 13th. You can see in the pictures below that is is pretty much complete and the last step is to do the final layer of asphalt and redirected traffic from the temporary bridge to the new overpass.
You can also see in the last picture that they have started to install the supports that will be needed to remove the temporary bridge which I assume will happen soon. This is a major milestone since this piece holds up the next steps in the project.
Friday, May 16, 2025
Direct Connect May 2025
Here is a look at the work going on at the old ramp from 42 South to 295 South. The old ramp is being removed to prepare of the completion of where the new main line overpass will link into 295 South.