Browning Road Overpass July 2024

Work on the second abutment for the new Browning Road Overpass appears almost complete. The concrete supports on the top of the abutment have been poured and the retaining wall next to it has been capped off. The Jersey barrier along the bottom of the wall has also been poured. 

 

The new Jersey barrier has also been extended part of the way under the temporary overpass.