I haven't posted any pictures recently since most of the work is going on in areas that are hard to photograph.
- Work continues on the widening of the Big Timber Creek bridge, with the new supports on both sides still be worked on.
- Concrete barriers are being poured along the ramp from 295 North to 42 South.
- Work continues in the median of 42 from 55 to the new ramps.
- The sidewalk along the new Creek Road overpass is almost complete which should allow this to completely re-open in it's new configuration
- Most of the rest of the work is going on up on the new ramps. All the steel supports are complete so they are now building the road deck.