More steel has been added to the ramp from 42 North to 295 South.
Thursday, December 23, 2021
Saturday, December 11, 2021
Missing Moved 12/2021
At the Big Timber Creek bridge they have started to pour the concrete or the abutments on both sides of the bridge and started to install more of the concrete beams.
Here is one of the beams waiting to be installed.
This is the section of the missing moves ramps between Creek Road and Leaf Ave. This section will be ground based so they have started to build up the earth to the height of the finished road.
Friday, December 3, 2021
Missing Moves 12/2021
More steel has started to go in for the Missing Moves project. This will be the ramp from 42 North to 295 South right before it passes over 42.
In this picture you can see the temporary supports for the next section of the ramp.
Beams staged along 42 North.