Friday, October 23, 2020

October 2020–Missing Moves

Here is a look at the work along 295 South just above creek road. It looks like they may be doing grouting to stabilize the ground here before they start building the ramp.

PXL_20201020_161103587-1


They have cleared space on the other side of the Creek Road overpass to make room for construction of the new overpass.

PXL_20201020_161103587-2


Here is a look at the new road that will connect Edgewood Ave to Benigno Ave.

PXL_20201019_193712298

PXL_20201019_193915044


The start of a new overpass support between Benigno Ave and 42.

PXL_20201019_193731514


This structure between Benigno Ave and 42 will be the transition between the ground based ramp from 42 North to the overpass.

PXL_20201019_193735291

Sunday, October 11, 2020

October 2020–Missing Moves


A temporary retaining wall has been built along the back of the warehouse that is between Creek Road and 295 North. You can also see they are excavating between the wall the the road.

PXL_20201011_131736514


Pilings being put in for another overpass support between 295 North and Creek Road.

PXL_20201011_131744259


The concrete wing wall has been cut off the Creek Road overpass abutment. This was needed to make room for the first part of the new overpass.

PXL_20201011_164502070

Saturday, October 10, 2020

October 2020–Missing Moves


Here is a look at the work on the Big Timber Creek bridge.

PXL_20200928_210648253


A temporary retaining wall has been build along the side of Creek Road to make room for the first part of the new overpass.

PXL_20200928_224357359


This picture was taken under the Creek Road overpass. You can see where a section of the overpass was removed.

PXL_20200928_210705228


Work along 295 North just above Creek Road. The highway will be widened into this area.

PXL_20200928_210705862

Saturday, October 3, 2020

September 2020–Missing Moves

A lot of progress has been made on the overpass supports near Coolidge Ave.


PXL_20200928_223122244


These appear to be supports for where the overpass will transition into a ground based part of the ramp.

PXL_20200928_223132384


On the left you can see the concrete form that is used to create the top portion of the support.

PXL_20200928_223137400


The beginning of a support near Harding Ave.

PXL_20200928_223159120