Here are a couple views of the progress on what will become the ramp from 42 North to 295 North.
Just beyond that ramp is a large pit that I assume will be used to construct foundations for an overpass support column.
Along 42 South, just below the Browning Road overpass, they have been installing noise barriers.
The have started to install re-bar for the concrete cap on the abutment.
They have been doing a lot of earthwork leading up to where the 295 main line will pass over the new tunnel. You can start to see the final shape of this section of the road. Just below the crane they have start to build the foundation for a sign structure.