The retaining wall along the cemetery

DSC02997


The wall on either side of the new ramp from 76 East to 295 North continues to take shape.

DSC03016


DSC03021


Continues work on the foundations for the new mainline overpass

DSC03003


Demolition of the first unit of the Bellmawr Park Mutual Housing will start soon.

DSC03008


They have already excavated the back yard.

DSC03018


Ground stabilization work going on along the ramp to the Southern part of 295 near Essex Ave.

DSC03005

Wednesday, May 9, 2018

Late April 2018


Work continues on the retaining walls that will form the sides of the new ramp from 76 East to 295 North. You can see the row of pilings on either side and the first couple courses of concrete panels on the far side.

DSC02978

DSC02982


Here is a view from 295 South

DSC02984


Work on the foundation for one of the supports for the new 295 main line overpass

DSC02980