Here is a look at the 76 East to 295 North tunnel. You can see a concrete pumper pouring the last section of the roof. The used plastic to wall off the section of the tunnel where the roof was being poured. I assume this was done to control the temperature.
A new section of retaining wall has been started just south of the Browning Road overpass.
They have also started a new section of noise barrier in this area.
Here is the view of the wall from the back.
Here are some views of the work along 42 South taken from the Browning Road overpass.
The area along the church parking has been cleaned up. I assume this will eventually get re-paved.
Here is a look at the supports for the 295 main line near the cemetery. They have recently started to construct retaining wall around the supports.
Here is a wider view of that area. On the far right are foundations for new noise barrier.
The supports for the temporary Browning Road overpass have been complete of quite some time now but there hasn’t been any more progress on the overpass since then.