Saturday, July 22, 2017

July 2017

Temporary light poles have been installed along the new ramp 76 East to 295 North. This ramp comes down between the current 295 North and South bound lanes. You can see the cars coming off the current ramp in the background of the first picture.

DSC02300

DSC02312


Here is a view from the new ramp from 295 South to 76 West. You can see the new 76 E to 295 N ramp in the background.

DSC02317


The new ramp from 76 East to 295 North is almost complete.

DSC02320


A new pumping station is being built near the new 76 East to 295 North ramp.

DSC02322


New sheet pile is being installed between the cemetery and 295 North.  This is right at the end of the retaining wall that was built during contract 2.

DSC02329

DSC02332


A look at the work going on along 76 East just before the Browning Road overpass.
DSC02327


More work going on next to the ramp from 76 East to 295 South just before Essex Ave. This is the start of the process to expand the new roadway that was built along the Bellmawr ball fields in earlier contracts to what will become the new 295 mainline.

DSC02337


Here are some not so great pictures of the progress of the new units for the Bellmawr Park Mutual Housing project.


Off of Essex Ave.

DSC02306


Off of Peach.

DSC02309

Sunday, July 9, 2017

July 2017

The majority of the work on the project continues to be along 295 from the Al-Jo curve down to the Essex Ave overpass.


The third sign structure that was over the road has been removed. Since this picture was taken it has been scrapped.

DSC02213


Drainage work between the Al-Jo curve on the right and the ramp from 76 East to 295 North.

DSC02218


The construction of a temporary retaining wall along 295 South just above the Browning Road overpass.


DSC02234


Here is another view of the same area

DSC02228

DSC02215


Work has begun between the 295 South ramp and the new mainline ramp just above Essex Ave.

DSC02237