Saturday, December 31, 2016

December 2016 Work Areas

Over the past few months work has only been going on in a couple area since contract 1 has been completed and contract 3 will not start until next year.

 

Most of the work is being done in this area. A new ramp is being built from 295 south to 76 west (highlighted in red). This ramp starts at the top of the new ramp that was built along 295 south and will connect to the existing ramp to 76. Work is also continuing on the new ramp from 76 east to 295 north. The ramp is pretty much complete up to where it will go over 76. Recently work started on the parts that will go over 76.

 

image

 

The other current work area along 295 north from around Bell Road up to Black Horse Pike. The left lane is currently close which drainage and paving work is done.