Thursday, November 23, 2023

Direct Connect November 2023

 For the last few months the focus of the work on the Direct Connect project has been the reconstruction of the collapsed section of roadway. 

Over the past few weeks they have been driving in pilings in the area of where the center of the road and these pilings have been capped off in concrete. This appears to be a temporary retaining wall that is allowing them to excavate out the front portion of the road which is where the problem that lead to the collapse occured. 







No comments:

Post a Comment