Move steel has been installed for the ramp from 42 North to 295 North. Long sections to connect the first cross beam to the second have been installed along with some small sections on the other side of the second cross beam. \
I-295/I-76/Route 42 Direct Connect
Sunday, June 28, 2026
Direct Connect June 2026
Wednesday, June 17, 2026
Direct Connect June 2026
Work continues to close up the gap in the retaining wall left by the temporary Browning Road overpass. Looks like one more course of panels and then the top cap to complete this.
The area next to Saint Joachim Parish is being used as a staging area for the retaining wall work. I assume this will be cleaned up once the retaining wall work is complete.
This is a picture of the northern portion of the new mainline overpass. Steel had been installed here a couple month ago and currently the concrete bridge deck is being poured.
Sunday, June 7, 2026
Direct Connect June 2026
Over the past few weeks more steel has been installed for the 295 main line overpass and connecting ramps. Here are some pictures of the ramp that will carry traffic from 42 North to 295 North. The ground based portion of this was built back in the early days of the project, this now starts the aerial portion.
Tuesday, May 12, 2026
Direct Connet May 2026
Sunday, May 3, 2026
Direct Connect April 2026
Sunday, March 29, 2026
Direct Connect March 2026
Here are a couple pictures showing the area where the temporary Browning Road overpass used to be. They are in the process of building the rest of the retaning wall to finish off that area.

















































