I-295/I-76/Route 42 Direct Connect
Sunday, November 15, 2026
Direct Connect November 2026
Thursday, November 12, 2026
Future 295 South to 42 South Ramp
In my last post I mentioned one of the major pieces of the project that will be part of the fourth contact, the new ramp from 295 South to 42 South. Currently, if you are coming down 295 south you would stay to the right and take the Al-Jo curve to get to 42 south. In the new configuration you will stay to the left and start down the existing ramp that takes you to 76 west towards Philadelphia. This ramp will split off to the left, go under 76 at an angle and come back up on the other side near where the Al-Jo curve currently ends and connect you to 42 south. This picture shows roughly where this ramp will be,
Here is a section of the plans showing that new tunnel.
The latest contract documents give a pretty good summary of how this will be built. It's a pretty complex multi-stage operation.
In stage 2A, two of the 76 west bound lanes will be shifted to go over this new bridge, the temporary sheet pile removed and reinstalled along the edge of the next to lanes. The whole process from stage 1 will then be repeated between the two sets of lanes.
Here is a cutaway view of what the final tunnel will look like.
Tuesday, November 10, 2026
Contract 4
In a recent post I mentioned that the new 295 south main line overpass and the new ramp from 42 north to 295 north would likely open next Spring which will also bring and end to Contact 3 of the project. NJDOT has recently put Contact 4 out for bid which is the final phase of the project, this should start next Spring and was estimated to be complete in 2032, but the contact sets a 2036 deadline for completion. Which bring up the question of what is left to be done. Here are the major task that remain to be completed in Phase 4. A lot of this work needs to be done in a specific sequence which is probably why it will take so long to complete.
- Opening of the 295 north bound mainline overpass.
- Construction of the new ramp from76 East to 295 south
- Construction of the new ramp from 295 South under 76 to 42 South.This is a signifant and complex part of the project. This will be done by constructing the first part of the tunnel beside 76, routing a lane of 76 over that part of the tunnel and then repeating this process lane by lane across both sides of 76.
- Widening of the 76 bridge over Kings Highway.
- Removal of the middle ramp that current carries 76 east traffic to 295 south, and the 295 north traffic to the 76 west express lanes. This will also allow for the staightening out of 42 in this area.
- Removal of the Al-Jo curve. This will also involve the removal of the 76 bridge over the curve which is another signficant part of the project.
- Final repaving of 76/42 over the full length of the project
- Construction of noise barreirs
- Addition of a new pump station. Construction and modifcaiton of water retention basins.
- Final new sign structures.
Wednesday, October 21, 2026
Direct Connect October 2026
Saturday, September 19, 2026
Direct Connect September 2026
Work continues on the new mainline overpass and the new ramp from 42 north to 295 north. Most of the steel is in which just one last section of the south bound lanes incomplete.
Sunday, September 13, 2026
Mainline Connection Details
In my previous post I mentioned that it is anticiapted that the new south bound mainline and ramp from 42 north to 295 north will open early next year but the northbound mainline will come some time afterwards. The difference in opening times for the north and south bound lanes doesn't have anything to with the time it will take to build them, but instead it is due to the logistics of connecting the north bound lanes on either end. Here I will describe what has to happen at each end of the new mainline and what I think the sequence of construction will be. I haven't seen any detailed plans for the final phase of construction so these are just my speculations. 42 Freeway recently did a video about this but I will dig into it in a bit more detail.
Lets start by looking at the North end of the project. Here is a picture of the area from mid June, 2026. At the top is 295 south which splits into the lanes going to the Al-Jo curve which re-connects to 295 and 42 South, and lanes going to 76 west. At the bottom of the picture are the lanes from from 295 north, 42 north and 76 east. In the middle is the new construction which will be 295 south, 295 north and the ramp from 42 morth.Sunday, August 30, 2026
Direct Connect 2026
Work continues on installation of the steel beams for the new mailine overpass. They are very close to putting in the spans over Browning Road.
While steel is going up on the mainline overpass, decking work is moving along on the ramp from 42 North to 295 North. Rebar has been placed on the first section and equipment has been put in place to smooth the new concrete bridge deck, so the first concrete pour is probably going to happen siin.











































