Sunday, March 29, 2026

Direct Connect March 2026

Here are a couple pictures showing the area where the temporary Browning Road overpass used to be. They are in the process of building the rest of the retaning wall to finish off that area. 





More steel has been installed for the 295 main line overpass. This being installed between the southern ground based part of the overpass up to where it could cross over 42. The pieces that go over 42 will eventually require nighttime road closures. 










Tuesday, March 3, 2026

Direct Connect February 2026

Over the last few weeks they have begun to install the steel structure of the new 295 mainline overpass. The section currently being built is the south bound section below Browning Road and will connect to the ground based section that has recently been built. This section doesn't go over any active portions of the highway so I assume this was done without any lane clousures. Evenutally they will need to put in steel over the highway which will require nighttime lane clousures. 





 

Sunday, January 25, 2026

Direct Connect January 2026

The removal of the bridge abutment for the temporary Browning Road overpass is almost complete. You can see the temporary retaining wall that was behind it. They will now complete the concrete retainin wall and join it to the permannt bridge abutment. 




Just south of the Browning Road overpass a temporary support has bee installed which will be used when the steel for the main line overpass is installed. 





Sunday, January 18, 2026

Browning Road Overpass January 2026

Here is picture fropm 1/17 showing the continued removal of the temporary abutment that was part of the temporary Browning Road overpass, removal is almost complete.  



Wednesday, January 14, 2026

Browning Road Overpass January 2026

This week they have started to remove the temporary bridge abutment that was holding up the termporary Browning Road overpass. Here is a picture from Tuesday..


This picture is from Wednesday. You can see a couple feet of the abutment has been removed and exposed the I-beam and wood retaining wall behind it. Once removed the mechancially stablized earth retaining wall will be completed up to the overpass. 




Friday, January 2, 2026

Direct Connect December 2025

There hasn't been a lot of progress recently that is easy to photograph, but I did find the Google Earth was updated recently for that area. Here is a picture from October of 2025.


Here I have marked up the location of the new overpasses in red and the support beams in yellow. Most of the columns for the supports are complete and some of the beams are already on site waiting to be installed. At the top of the picture you can see the two sections where steel beams have already been installed. 





Sunday, November 23, 2025

Direct Connect November 2025

 Here is a look at the progress on the raised section that will bring the north bound traffic on 295 up to the new mainline overpass. 






More steel has been set leading up to the Browning Road overpass.