Over the past few weeks more steel has been installed for the 295 main line overpass and connecting ramps. Here are some pictures of the ramp that will carry traffic from 42 North to 295 North. The ground based portion of this was built back in the early days of the project, this now starts the aerial portion.
I-295/I-76/Route 42 Direct Connect
Sunday, June 7, 2026
Direct Connect 2026
Tuesday, May 12, 2026
Direct Connet May 2026
Over the weekend a new traffic pattern was put in place on 76 East / 42 South. Three lanes going to 42 South have been shifted to the right and along with a single lane coming off the Al-Jo curve they now pass under the new 295 mainline overpass that has been built over the past few months. The single lane from 76 East to 295 South has also been shifted to the right and joins back to the ramp closer to 42.
I believe these lane shifts are needed to make room for the installation of the remaining steel for the 295 mainline overpass.
42Freeway has posted a great video that shows a drive through of the new pattern along with aerial views.
Here are some of my photos driving through the new pattern.
On the right are the two lanes from the Al-Jo curve going to 295 South, in the middle is the lane from the Al-Jo curve going to 42 South, and on the left are the lanes from from 76 East.
Another thing to note is that recently a crane has appeared ont he small piece of ramp which will eventually carry 42 North traffic to 295 North. This likely means that installation of steel for that ramp will start soon.
Sunday, May 3, 2026
Direct Connect April 2026
Here is an overview picture of the most active area of the project. On the left in the southern portion of the new main line overpass. It starts with a ground based portion and transitions into the recently added steel that will extend over 42 and Browning Road. The partial ramp on the right was built in an earlier phase of the project and will eventually carry traffic from 42 North to 295 North.
First sections of steel have been installed over the past few weeks. Temporary railings have been installed so work can begin on the bridge deck for this section.
Steel has been installed up to the point where it would pass over the current travel lanes. You can also see that metal brackets have been added to the tops of the columns where steel beams will be attached.
Work continues to close up the hole in the retaining wall where the temporary Browning Road overpass was. A couple rows of wall panels have been installed and they have poured the concrete barrier along the botton.
Sunday, March 29, 2026
Direct Connect March 2026
Here are a couple pictures showing the area where the temporary Browning Road overpass used to be. They are in the process of building the rest of the retaning wall to finish off that area.

More steel has been installed for the 295 main line overpass. This being installed between the southern ground based part of the overpass up to where it could cross over 42. The pieces that go over 42 will eventually require nighttime road closures.
Tuesday, March 3, 2026
Direct Connect February 2026
Over the last few weeks they have begun to install the steel structure of the new 295 mainline overpass. The section currently being built is the south bound section below Browning Road and will connect to the ground based section that has recently been built. This section doesn't go over any active portions of the highway so I assume this was done without any lane clousures. Evenutally they will need to put in steel over the highway which will require nighttime lane clousures.
Sunday, January 25, 2026
Direct Connect January 2026
The removal of the bridge abutment for the temporary Browning Road overpass is almost complete. You can see the temporary retaining wall that was behind it. They will now complete the concrete retainin wall and join it to the permannt bridge abutment.
Just south of the Browning Road overpass a temporary support has bee installed which will be used when the steel for the main line overpass is installed.
Sunday, January 18, 2026
Browning Road Overpass January 2026
Here is picture fropm 1/17 showing the continued removal of the temporary abutment that was part of the temporary Browning Road overpass, removal is almost complete.
Subscribe to:
Posts (Atom)











































