Sunday, February 28, 2021

Missing Moves - February 2021

At the Big Timber Creek bridge they have started to install pilings that will support the new center section of the bridge.




Work along 295 North where the new ramps will cross over Creek Road.


Here is a look at that area from Creek Road. The support on the right is for the ramp from 42 North to 295 South and will cross over 295 to join to the south bound side. The support on the left is for the ramp from 295 North to 42 South and will be a ground based ramp.


Center support is being built for the new Creek Road overpass.



Here is the approach to the the Creek Road overpass. You can see how the overpass will be shifted towards the north.


Here is the other side of the overpass.


The ramp from 42 North to 295 South






Another overpass support being built near the exit from 42 South onto Leaf Ave and Harding Ave.


Work between 42 North and Benigno Ave.





No comments:

Post a Comment