A few weeks ago the new Browning Road overpass opened, so work has now turned to removing the temporary overpass. Most of the bridge decking has been removed and the temporary support columns have been setup. I assume this will be removed just like it was installed, sliding it over to the cemetery side and disassembling it piece by piece.
Friday, July 11, 2025
Tuesday, June 24, 2025
Browning Road Overpass Now Open!
Thursday, June 12, 2025
Browning Road Overpass June 2025
The new Browning Road overpass is nearing completion and word is that it will open on June 13th. You can see in the pictures below that is is pretty much complete and the last step is to do the final layer of asphalt and redirected traffic from the temporary bridge to the new overpass.
You can also see in the last picture that they have started to install the supports that will be needed to remove the temporary bridge which I assume will happen soon. This is a major milestone since this piece holds up the next steps in the project.
Friday, May 16, 2025
Direct Connect May 2025
Here is a look at the work going on at the old ramp from 42 South to 295 South. The old ramp is being removed to prepare of the completion of where the new main line overpass will link into 295 South.
Sunday, May 11, 2025
Direct Connet May 2025
Here is a look at the support columns being built betwen the north and south bound lanes of 42. Some of these will be for the new 295 mainline overpass, others will be for the ramp from 42 north to 295 north. You can see the start of that ramp on the right which was built quite some time ago.

Sunday, May 4, 2025
Browning Road Overpass April 2025
Here are some pictures of the current state of the Browning Road overpass. Utility lines have been installed and rebar placed for the bridge deck. Equipment to smooth the concrete has been put in place so pouring of the concrete bridge deck should happen soon.
Sunday, April 27, 2025
Direct Connect April 2025