Preparation work has started on the area around the collapsed wall to get ready for reconstruction which should start soon.
Sunday, October 30, 2022
Direct Connect October 2022
The shoulder along the ramp from 42 North to 295 North has been widened and some drainage improvements have been made.
Wednesday, October 26, 2022
Creek Road Overpass
On the Creek Road overpass over 295, traffic has been shifted onto the newly constructed south side of the bridge. The north side once again been blocked off so the final work can be complete there which will include adding the pedestrian walkway.
Sunday, October 16, 2022
Missing Moves October 2022
With the Creek Road overpass mostly complete there is now room to complete the ramp that will come from 42 North to 295 South
Work continues on the approach to the ramp from 295 North to 42 South. The highway is being widened and curbing and barriers have started to go in.
Saturday, October 8, 2022
Missing Moves October 2022
Work has begun on the support in the center median of 42. This is the final support needed to connect the two parks of the missing moves ramp that is already under construction.
The ground based section of the ramp is also coming along. Here is a picture of it from Creek Road.
Sunday, September 18, 2022
Direct Connect September 2022
Now that work is almost complete on the first of the new Browning Road overpass abutments the barriers have been removed and new paving have taken place from the Al-Jo curve down to the 295/42 split.
Sunday, September 11, 2022
Missing Moved September 2022
Work continues to widen the north bound side of 295 from Delsea Drive up to new ramp to 42 south. Land is being cleared, drainage installed and the area is being prepped for paving.
Sunday, August 28, 2022
Direct Connect August 2022
Work on the Direct Connect project continues to be focused on the Browning Road overpass replacement. The first of the new bridge abutment is nearing completion.
42freeway.com is reporting that reconstruction of the collapsed section of the project should be starting in the fall, although the temporary lane closure for prep work mentioned in the article doesn't appear to have happened.
Subscribe to:
Posts (Atom)




































