With the new section of the Creek Road overpass complete demolition of the other half has started.
Friday, October 29, 2021
Tuesday, October 19, 2021
Browning Road Overpass
The temporary Browning Road overpass has finally opened making way for he demolition and reconstruction of the existing bridge.
Here are some pictures from before the opening of the temporary bridge.
Here are some pictures driving over the new bridge. It is one lane in each direction, with a sperate pedestrian walkway down the side opposite the old overpass.
Monday, October 11, 2021
Missing Moves 10/2021
Work has started on the retaining walls for the ramp from 295 North to 42 South.
Tuesday, September 14, 2021
Creek Road Overpass
Traffic on the Creek Road overpass over 295 has been moved over to the newly constructed section. This will clear the way to demolish and rebuild the other half.
Saturday, September 4, 2021
Missing Moves August 2021
Support for the missing moves ramp along Creek Road. The front side will support the overpass over Creek Road, the back side will be a ground based ramp.