Sunday, April 14, 2019

March 2019 - Part 4

This picture is a little blurry but gives an interesting view of the work going on along 42 South just beyond the Browning Road overpass. You can see two distinct paths in this area. On the right is piece of the what will become the new 295 main line overpass. On the left is what will become the new ramp from 76 East to 295 South. You can see how this ramp rises up from where it will pass under Browning Road. 




Saturday, April 6, 2019

March 2019 - Part 3

Here is a photo of the work going on along 42 North where the new ramp to 295 North will eventually be. 


Here is a closer look at that area.







Back during contract one these support columns were built. Recently forms have ben added to the top of them. These will eventually support the 295 main line overpass.


Here is a look at more of the supports for the overpass. Not much work has happened here recently.




On the other side of the road some more work has been done on the end of this part of the ramp. They will eventually finish off the end of the that section so it can support steel beams for the next section.











Friday, March 22, 2019

March 2019 - Part 2

Here is a recent picture of the area between the north and south bound lanes of 295 where the start of the new mainline overpass will eventually begin.


You can see the sides of the overpass where it goes over the tunnel, I have marked these in blue. This gives you an idea of home the end of the overpass will shaped and link up with the rest of the road.



Work also continues over the tunnel on the noise barrier along the cemetery. 

Thursday, March 21, 2019

March 2019 - Part 1

There has been a lot of work going on over the past few weeks. First is the tunnel to North bound 295. A few weeks ago the lanes from from 76 East were routed into the tunnel along with the ones coming from 42 North. This is a much better traffic pattern then it was with just the lanes from 42. There are not five lanes going into the tunnel which merge down to four just after. The traffic lights will normally be green and will only be changed if there is a need to close one of the lanes in the tunnel..

Here is the inside of the tunnel where you can see the large number of lights on the wall. The number of lights in use varies with the time of day.



Here is the exit of the tunnel. You can also see the rock that has been put on the slope below the cemetery and the finished retaining wall capped off with a fence.




Saturday, February 23, 2019

Febraury 2019


A few weeks ago the traffic from 42 North going to 295 N was re-routed into the newly constructed tunnel. Here you can see the three lanes going into the tunnel where they merge down into two. The traffic lights are normally green and are only used when they need to close a lane in the tunnel


DSC03571


The tunnel walls are lined with a large number of lights. The number of lights that are turned on seems to vary by the time of day.

DSC03573


DSC03587


At the other end of the tunnel, paving work is being done to get ready for when the 76 East ramp lanes are re-routed into the tunnel.

DSC03577


Work continues on the retaining wall about the tunnel

DSC03581


DSC03583


Work also continues along 42 North by the ramp from 295. This is where the ramp from 42 North to 295 North will eventually go.

DSC03566


DSC03567

Sunday, February 3, 2019

February 2019

A new work area has started up recently along 42 North just after the ramp from 295 South. This is where the ramp from 42 North up to the new 295 main line will eventually be.


 Work on the other side of 42/76 has slowed down recently, although they still do continue to put in pilings in this pit. I assume there will be a support for the overpass here.



The most activity recently has been around the new tunnel along 295 North. By the time you read this traffic coming off of 42 North will have been re-routed into this tunnel. Over the next few weeks the ramp from 76 East will be re-routed into that tunnel also which will free up room to continue construction of the main line overpass.




Some finishing work has been done at the end of the tunnel. The hill side has been cleaned up and covered in stone and a railing as been added to the top of the retaining wall.

Friday, January 4, 2019

January 2019


Here is a look at the entrance to the tunnel that will eventually carry the 76 West to 295 North ramp. Short term all the traffic lanes going north on 295 will route through here to make room for other construction. On the right you can see the retaining being capped off.


DSC03503


Since that picture was taken traffic lights have been added before the tunnel. I believe these will be used to open and close lanes in the tunnel.

20190103_154015


Now that the tunnel is complete they are using the top to provide access needed to finish the top of the retaining wall.

DSC03491


Construction continues on the retaining wall between 42 and the cemetery. At the end of the wall are the supports for the 295 main line overpass.

20190103_154033


DSC03494


DSC03502


A new section of noise barrier has been built along the cemetery.

DSC03497


Work continues just below the Browning Road overpass. Part of a noise barrier has been constructed and work continues on foundations for more supports for the main line overpass.

DSC03486