Sunday, April 14, 2019
March 2019 - Part 4
Saturday, April 6, 2019
March 2019 - Part 3
Friday, March 22, 2019
March 2019 - Part 2
Thursday, March 21, 2019
March 2019 - Part 1
Saturday, February 23, 2019
Febraury 2019
A few weeks ago the traffic from 42 North going to 295 N was re-routed into the newly constructed tunnel. Here you can see the three lanes going into the tunnel where they merge down into two. The traffic lights are normally green and are only used when they need to close a lane in the tunnel
The tunnel walls are lined with a large number of lights. The number of lights that are turned on seems to vary by the time of day.
At the other end of the tunnel, paving work is being done to get ready for when the 76 East ramp lanes are re-routed into the tunnel.
Work continues on the retaining wall about the tunnel
Work also continues along 42 North by the ramp from 295. This is where the ramp from 42 North to 295 North will eventually go.
Sunday, February 3, 2019
February 2019
The most activity recently has been around the new tunnel along 295 North. By the time you read this traffic coming off of 42 North will have been re-routed into this tunnel. Over the next few weeks the ramp from 76 East will be re-routed into that tunnel also which will free up room to continue construction of the main line overpass.
Some finishing work has been done at the end of the tunnel. The hill side has been cleaned up and covered in stone and a railing as been added to the top of the retaining wall.
Friday, January 4, 2019
January 2019
Here is a look at the entrance to the tunnel that will eventually carry the 76 West to 295 North ramp. Short term all the traffic lanes going north on 295 will route through here to make room for other construction. On the right you can see the retaining being capped off.
Since that picture was taken traffic lights have been added before the tunnel. I believe these will be used to open and close lanes in the tunnel.
Now that the tunnel is complete they are using the top to provide access needed to finish the top of the retaining wall.
Construction continues on the retaining wall between 42 and the cemetery. At the end of the wall are the supports for the 295 main line overpass.
A new section of noise barrier has been built along the cemetery.
Work continues just below the Browning Road overpass. Part of a noise barrier has been constructed and work continues on foundations for more supports for the main line overpass.